Weekly Project Update
MNTHS

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Completed grade beam excavation.
- Completed 1st side of forms for grade beams
- Received rebar for grade beams.
- Received void form boxes.
-
-

Void form delivery
NEXT WEEK'S ACTIVITIES
- Install soil retainers, void form boxes and rebar in grade beams on grid lines A,!, and I
- Complete form work on gridlines A, 1, and I
-
-
-

-
Form work on grid line 10 near a support pier.

Installing 1st side of grade beam form work.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.