Weekly Project Update
Manor ISD Kitchen Serving Lines (Manor High School)
THIS WEEK'S ACCOMPLISHMENT
- Wall tile at 90% complete
- Wallboard installed
- Tape and float complete
- Fire alarm devices set
- Ceiling grid installed in serving line area
- Lights set in grid and connected

Wall and floor tile 90% complete
NEXT WEEK'S ACTIVITIES
- Install overhead doors
- Install vinyl flooring
- Texture and paint front wall and door openings
- Finish ceiling grid, above ceiling rough, set grilles, and get inspections
- Reinstall old kitchen equipment and install new serving lines

- Start installing ceiling tile
Tape and float complete

Ceiling grid 80% complete at serving area (waiting on OH doors to finish)
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.