top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Manor ISD Kitchen Serving Lines (Manor High School)

Placeholder

THIS WEEK'S ACCOMPLISHMENT

    Wall tile at 90% complete
    Wallboard installed
    Tape and float complete
    Fire alarm devices set
    Ceiling grid installed in serving line area
    Lights set in grid and connected
Excavation 1.jpg

Wall and floor tile 90% complete

NEXT WEEK'S ACTIVITIES

    Install overhead doors
    Install vinyl flooring
    Texture and paint front wall and door openings
    Finish ceiling grid, above ceiling rough, set grilles, and get inspections
    Reinstall old kitchen equipment and install new serving lines
Excavation 1.jpg
    Start installing ceiling tile

Tape and float complete

Excavation 1.jpg

Ceiling grid 80% complete at serving area (waiting on OH doors to finish)

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page