THIS WEEK'S ACCOMPLISHMENT

    Completing wall and parapet framing
    Continuing with electrical rough in at gym
    Start roofing activities at gym, installing roof blocking
    Installed new fire hydrant at the MPB
    Continuing with wall panel installation on the east walls of MPB
    Started receiving the stone deliveries for the gym walls
Excavation 1.jpg

Exterior wall framing at Gym

NEXT WEEK'S ACTIVITIES

    Continue with the roof installation at the Gym
    Continue with the installation of lateral bracing and other framing details at the gym walls.
    Insulate exterior parapet walls and start installing the densglass sheeting on exterior walls
    Install roof access ladder at the Gym
    Continue with wall panel installation at MPB
Excavation 1.jpg
    Complete the installation of the fire sprinkler piping at the Gym

New weight room at Gym

Excavation 1.jpg

Wall panel installation at MPB