THIS WEEK'S ACCOMPLISHMENT
- subgrade backfill is ready to blue top at Gym
- Mucking out of MPB site is complete and ready to remobilize
- Electrical conduit to pole light is complete
- Pier drilling at MPB is scheduled to resume on Monday 2-20-2-23
-
-

Electrical conduit at pole light
NEXT WEEK'S ACTIVITIES
- Blue top building pad at Gym
- Building corner and pier layout at Gym foundation
- Pier drilling and grade beams to resume
-
-

-
Gym subgrade ready to blue top

Gym subgrade ready to blue top
LOOK AHEAD SCHEDULE