THIS WEEK'S ACCOMPLISHMENT

    subgrade backfill is ready to blue top at Gym
    Mucking out of MPB site is complete and ready to remobilize
    Electrical conduit to pole light is complete
    Pier drilling at MPB is scheduled to resume on Monday 2-20-2-23
Excavation 1.jpg

Electrical conduit at pole light

NEXT WEEK'S ACTIVITIES

    Blue top building pad at Gym
    Building corner and pier layout at Gym foundation
    Pier drilling and grade beams to resume