THIS WEEK'S ACCOMPLISHMENT

    Main roof of Gym is complete
    Framing and densglass on exterior walls to complete Friday
    Roof ladder is installed at Gym
    Duct install is underway at Gym
    Continuing with wall panel installation on the south walls of MPB
    MEP subs mobilizing at MPB
Excavation 1.jpg

Framing and densglass install at Gym

NEXT WEEK'S ACTIVITIES

    Continue with wall panel installation at MPB
    Continue with MEP rough in at MPB
    Continue duct install at Gym
    Continue electrical rough in at Gym
    Continue with waterproofing at Gym exterior walls
Excavation 1.jpg
    Start framing, electrical and plumbing work in existing weight room at Gym

Installation of roof ladder at Gym

Excavation 1.jpg

Wall panels at south wall of MPB