Weekly Project Update
Manor Senior High School Practice Gym and MPB
THIS WEEK'S ACCOMPLISHMENT
- Completed installation of new waste water line and man hole, system is complete and operational
- Completed drilling all piers that do not require casing
- Starting installation of grade beams
- Restarting the installation of the remaining storm drain lines
-
-

Installing the new manhole at Gym
NEXT WEEK'S ACTIVITIES
- Continue grade beam installations at MPB
- Continue with drilling and casing of the remaining piers at MPB
- Continue installation of storm drain piping at the Gym
- Start demo of existing storm drain piping at Gym
-

-
Grade beam installation at MPB

Piers at MPB to be drilled and cased
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.