Weekly Project Update

Manor Senior High School Practice Gym and MPB

Placeholder

THIS WEEK'S ACCOMPLISHMENT

    Completed installation of new waste water line and man hole, system is complete and operational
    Completed drilling all piers that do not require casing
    Starting installation of grade beams
    Restarting the installation of the remaining storm drain lines
Excavation 1.jpg

Installing the new manhole at Gym

NEXT WEEK'S ACTIVITIES

    Continue grade beam installations at MPB
    Continue with drilling and casing of the remaining piers at MPB
    Continue installation of storm drain piping at the Gym
    Start demo of existing storm drain piping at Gym
Excavation 1.jpg

Grade beam installation at MPB

Excavation 1.jpg

Piers at MPB to be drilled and cased

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.