THIS WEEK'S ACCOMPLISHMENT
- Completed masonry at Gym
- Completed steel erection at Gym
- Erected major structural steel at MPB
- Installed roof curbs at Gym
-
-

Completed masonry at Gym
NEXT WEEK'S ACTIVITIES
- Start metal stud framing at Gym
- Start overhead electrical rough in at Gym
- Install steel parapet wall supports at gym roof
- Continue with steel erection at MPB
-

-
Completed masonry at Gym

MPB steel erection
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.