THIS WEEK'S ACCOMPLISHMENT
- New support curbs installed for HRUs
- Support curbs flashed in and water proofed
-
-
-
-

New support curb set in place
NEXT WEEK'S ACTIVITIES
- Set new curb adapters on saturday
- Fly up remaining HRUs, and OAU on monday 11-21-22
- Connect power, condensate, and gas to new units
- Start-up all new units by the end of the week
-

-
support curb layout

support curbs leveled
LOOK AHEAD SCHEDULE