Weekly Project Update

Ojeda Middle School HVAC Replacement

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    New support curbs installed for HRUs
    Support curbs flashed in and water proofed
Excavation 1.jpg

New support curb set in place

NEXT WEEK'S ACTIVITIES

    Set new curb adapters on saturday
    Fly up remaining HRUs, and OAU on monday 11-21-22
    Connect power, condensate, and gas to new units
    Start-up all new units by the end of the week
Excavation 1.jpg

support curb layout

Excavation 1.jpg

support curbs leveled

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.