top of page


Weekly Project Update
Ojeda Middle School HVAC Replacement

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- Cafeteria ceiling replaced
- Admin air online
- GSHPs startup 25% complete
- Split system start up 60% Complete
- Geo pump install 75% complete
- Installation of new gas lines started

Cafeteria ceiling replacement in progress
NEXT WEEK'S ACTIVITIES
- Begin installing RTUs
- Complete GSHP start up 800 and 700 wings
- Complete split systems start ups except library
- Install remaining RTU curbs
- Continue running new gas lines

- Commission 800 and 700 wings
New Gas line installation ongoing

Geo pumps installed at GSHPs
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page