Weekly Project Update

Ojeda Middle School HVAC Replacement

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Cafeteria ceiling replaced
    Admin air online
    GSHPs startup 25% complete
    Split system start up 60% Complete
    Geo pump install 75% complete
    Installation of new gas lines started
Excavation 1.jpg

Cafeteria ceiling replacement in progress

NEXT WEEK'S ACTIVITIES

    Begin installing RTUs
    Complete GSHP start up 800 and 700 wings
    Complete split systems start ups except library
    Install remaining RTU curbs
    Continue running new gas lines
Excavation 1.jpg
    Commission 800 and 700 wings

New Gas line installation ongoing

Excavation 1.jpg

Geo pumps installed at GSHPs

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.