THIS WEEK'S ACCOMPLISHMENT
- All remaining curb adapters set
- Additional support curbs installed
- All remaining units set on roof
- Power installed to all remaining units
- Gas piped in to remaining HRUs
- HRUs 1-4, and OAU 1 start up complete

HRU 7 installed
NEXT WEEK'S ACTIVITIES
- Start up HRU 7
- Run secondary 120v power to HRUs
- Final gas inspection
- Complete condensate lines installation
- Controls tie in to new units

-
OAU 1 installed

HRUs 1-4 installed
LOOK AHEAD SCHEDULE