Weekly Project Update
Region 13 La Grange

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- Abatement Completed
- Floors demo complete
- Light fixture demo started
- Ceiling demo started
- HVAC demo started
- HVAC pre construction function test complete

Demo started
NEXT WEEK'S ACTIVITIES
- Complete ceiling demo
- Begin above ceiling electrical demo
- Demo remainder of interior walls
- Begin HVAC rough
- Begin Wall layout area A (Back of building)

- Begin Electrical rough
Flooring and counters removed

Ceiling demo and fitting room demo