Weekly Project Update

Region 13 La Grange

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Abatement Completed
    Floors demo complete
    Light fixture demo started
    Ceiling demo started
    HVAC demo started
    HVAC pre construction function test complete
Excavation 1.jpg

Demo started

NEXT WEEK'S ACTIVITIES

    Complete ceiling demo
    Begin above ceiling electrical demo
    Demo remainder of interior walls
    Begin HVAC rough
    Begin Wall layout area A (Back of building)
Excavation 1.jpg
    Begin Electrical rough

Flooring and counters removed

Excavation 1.jpg

Ceiling demo and fitting room demo

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.