THIS WEEK'S ACCOMPLISHMENT

    First coat of paint applied to area C
    Area A framing started
    Corridor ceilings framing complete
    Corridor ceilings sheet rock started
    Utility tie in to manhole complete
    Area B two side sheet rock 90% complete
Excavation 1.jpg

Utility line from building to man hole

NEXT WEEK'S ACTIVITIES

    Begin to first coat paint area B
    Complete plumbing top-out
    One side sheet rock area A
    Complete two layers of sheet rock on corridors
    Backfill utility line trench in parking lot
Excavation 1.jpg
    Pull wire for area C

First coat of paint in Area C

Excavation 1.jpg

Corridor ceilings sheet rock started and walls taped/floated

LOOK AHEAD SCHEDULE