top of page


Weekly Project Update
Region 13 Marble Falls

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Plumbing underground completed and inspected and poured back
- Starting challenge of getting a/c units in time
- Demo 90% complete
- Started conversation of low voltage requirements of completing on time.
- Dug and formed footings for interior added steel columns and new a/c pads
- Starting hanging duct straps where new duct will install next week.

Plumbing underground ready for concrete pour back.
NEXT WEEK'S ACTIVITIES
- Rough in walls electric
- Start sheet rock patches
- Get a/c approved and ordered
- Try and get most submittals in for approval
- Duct arrives and starts hanging

- Get steel approved and ordered for partition supports.
Most demolition completed

Underground plumbing completed and inspected
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page