Weekly Project Update

Region 13 Marble Falls

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Plumbing underground completed and inspected and poured back
    Starting challenge of getting a/c units in time
    Demo 90% complete
    Started conversation of low voltage requirements of completing on time.
    Dug and formed footings for interior added steel columns and new a/c pads
    Starting hanging duct straps where new duct will install next week.
Excavation 1.jpg

Plumbing underground ready for concrete pour back.

NEXT WEEK'S ACTIVITIES

    Rough in walls electric
    Start sheet rock patches
    Get a/c approved and ordered
    Try and get most submittals in for approval
    Duct arrives and starts hanging
Excavation 1.jpg
    Get steel approved and ordered for partition supports.

Most demolition completed

Excavation 1.jpg

Underground plumbing completed and inspected

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.