Weekly Project Update
Spicewood ES

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Started classroom air conditioners on 300,400, & 500 wing.
- Completed roof hydrant installation.
- Reinstalled light fixtures in main corridors.
- Began moving furniture in classrooms.
- Installed electrical panels DPA and HVA
- Started RTU 5 that supplies the gym.

Patched VCT and installed cove base in corridors 200,300,400, & 500.
NEXT WEEK'S ACTIVITIES
- Startup the balance of the air conditioning equipment.
- Complete above ceiling inspections.
- Start installation of the FRL wainscoting trim.
- Complete fixture and toilet accessories
- Final inspections

- Final clean corridors and restrooms
Restroom fixtures.

Toilet partitions in renovated restrooms.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.