Weekly Project Update
St. Julian's

James Castillo
THIS WEEK'S ACCOMPLISHMENT
- Found leak on 16" and repaired
- Passed Hydrostatic pressure test on 16" water main and 6" fire main
- Got Belfry tower and more steel erected
-
-
-

NEXT WEEK'S ACTIVITIES
- collect Bacti samples on 16" water main
- Turn 16" water line over to City
-
-
-

-

LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.