THIS WEEK'S ACCOMPLISHMENT

    Paint Structure at Apparatus Bay
    Sidewalks and Equipment Pads
    Mezzanine Framed And Decked
    Metal Decking at Living Quarters
    Waterproofing
Excavation 1.jpg

Entry Sidewalk Ready for Concrete

NEXT WEEK'S ACTIVITIES

    Air Barrier at Living Quarters
    Stone Veneer Wall Ties
    Light Pole Bases
    Dumpster Pad
    Rigid Roof Insulation at Living Quarters
Excavation 1.jpg

Ready for Exterior Finishes

Excavation 1.jpg

Waterproofing Underway

LOOK AHEAD SCHEDULE