THIS WEEK'S ACCOMPLISHMENT

    Concrete Paving Blue Tops
    Approaches Saw Cut & Removed
    Concrete Paving Layout
Excavation 1.jpg

LQ Truss Progress

NEXT WEEK'S ACTIVITIES

    LQ Trusses
    Concrete Paving Forms
    Concrete Paving Reinforcing Steel
    Concrete Paving 1st Pour
Excavation 1.jpg

East Side Storm Pipe Complete

Excavation 1.jpg

Paving Blue Tops Underway

LOOK AHEAD SCHEDULE