Weekly Project Update
TCESD 2 STATION 6
THIS WEEK'S ACCOMPLISHMENT
- Concrete Paving North Drive Complete
- Erect Structural Steel
- CMU Walls AB East
- Plumbing & Electrical Wall Rough In at LQ
- Pond Head Walls Formed Ready for Concrete
-

Entry Structural Steel In Place
NEXT WEEK'S ACTIVITIES
- Set Trusses at Structural Steel
- CMU Walls AB East
- Place Concrete at Columns
- Frame Exterior Walls LQ
- Dens Glass Exterior Walls

-
CMU Walls Underway

Structural Steel Complete
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.