Weekly Project Update
TCESD 2 STATION 6

Jeff Krueger
THIS WEEK'S ACCOMPLISHMENT
- Concrete Paving Prep
- Concrete Paving Lime Stabilization
- LQ Trusses In Progress
- Saw Cutting at Approaches
- Retaining Wall Backfill
-

LQ Trusses Underway
NEXT WEEK'S ACTIVITIES
- LQ Trusses
- Concrete Paving Lime Stabilization
- Survey Set Stakes at Parking & Drives
- Downspout Storm Pipe East Side
- Set Forms at Concrete Paving

-
Paving Prep

Ready For Lime
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.