top of page


Weekly Project Update
TCESD 2 STATION 6
THIS WEEK'S ACCOMPLISHMENT
- GB Concrete Placement at AB
- Oil Separator Tank Installed
- GB Forms Wrecked at AB
- AB Soil Retainers Underway
- AB Backfill Getting Started
-

Oil Separator Tank Installed
NEXT WEEK'S ACTIVITIES
- LQ Termite Pre Treat
- LQ Void Forms & Vapor Barrier
- LQ Slab Reinforcing Steel
- AB Under Slab Plumbing Rough In
- AB Under Slab Electrical Rough In

-
Wastewater Line Landscaping

AB Grade Beams Ready to Backfill
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page