THIS WEEK'S ACCOMPLISHMENT
- Pier Reinforcing Steel Delivered
- Drilling Rig On Site
- Storm Pipe Inspected and Covered Up
- Water Line Layout
- Pier Cages Fabricated
-

Storm Pipe Wrapping Up
NEXT WEEK'S ACTIVITIES
- Batter Board Install
- Start Drilling Piers
- Start Water Line Install
- Start On Site Waste Water Line
-

-
Pier Cages Underway

Drilling Rig On-Site