THIS WEEK'S ACCOMPLISHMENT

    Pier Reinforcing Steel Delivered
    Drilling Rig On Site
    Storm Pipe Inspected and Covered Up
    Water Line Layout
    Pier Cages Fabricated
Excavation 1.jpg

Storm Pipe Wrapping Up

NEXT WEEK'S ACTIVITIES

    Batter Board Install
    Start Drilling Piers
    Start Water Line Install
    Start On Site Waste Water Line
Excavation 1.jpg

Pier Cages Underway

Excavation 1.jpg

Drilling Rig On-Site

LOOK AHEAD SCHEDULE