top of page


Weekly Project Update
AGILENT TECHNOLOGIES FLOOR 1 OFFICE RENOVATION

Pat Tims
THIS WEEK'S ACCOMPLISHMENT
- POLISHED PANTRY FLOOR
- RESILIENT CHANNEL INSTALLED
- DRYWALL INSTALLATION GOING UP ON GYM WALL
- CEILING GRID INSTALLATION STARTED
-
-

DRYWALL INSTALLATION COMPLETE
NEXT WEEK'S ACTIVITIES
- CEILING GRID COMPLETED
- LIGHT NSTALLATION COMPLETED
- MILLWORK INSTALLED
- PLUMBING FIXTURES INSTALLED
- HVAC DEVICES INSTALLED

- PAINT COMPLETED
CEILING GRID INSTALLATION STARTED

PANTRY FLOOR POLISHING COMPLETED
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page