Weekly Project Update

AGILENT TECHNOLOGIES FLOOR 1 OFFICE RENOVATION

Placeholder

Pat Tims

THIS WEEK'S ACCOMPLISHMENT

    POLISHED PANTRY FLOOR
    RESILIENT CHANNEL INSTALLED
    DRYWALL INSTALLATION GOING UP ON GYM WALL
    CEILING GRID INSTALLATION STARTED
Excavation 1.jpg

DRYWALL INSTALLATION COMPLETE

NEXT WEEK'S ACTIVITIES

    CEILING GRID COMPLETED
    LIGHT NSTALLATION COMPLETED
    MILLWORK INSTALLED
    PLUMBING FIXTURES INSTALLED
    HVAC DEVICES INSTALLED
Excavation 1.jpg
    PAINT COMPLETED

CEILING GRID INSTALLATION STARTED

Excavation 1.jpg

PANTRY FLOOR POLISHING COMPLETED

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.