THIS WEEK'S ACCOMPLISHMENT
- Electrical rough in under way for area A5 and A6
- HDS header at the nurses station Sleeping units installed
- The relocations of sleeping units to accommodate the fire wall install interference completed
- Plumbing rough in complete in area A4 and A6 completed
- Plumbing tie in will be taking place this Saturday 17th
-

HDS header at nurses station installed
NEXT WEEK'S ACTIVITIES
- Install and complete the HDS headers in area A7
- Complete electrical rough in in area A6 and A5
- Start electrical rough in of area A7
- Start on siding of sheet rock for area A4 A5 and A6
- Relocate the sprinkler line in area A8 for fire wall install

-
patch work of old penetration complete

roof top unit in place, ready for there rough in and electrical
LOOK AHEAD SCHEDULE