Weekly Project Update

BBTCS STEP DOWN RENOVATION

Placeholder

Keith Farrell

Jan 16, 2026

THIS WEEK'S ACCOMPLISHMENT

    Electrical rough in under way for area A5 and A6
    HDS header at the nurses station Sleeping units installed
    The relocations of sleeping units to accommodate the fire wall install interference completed
    Plumbing rough in complete in area A4 and A6 completed
    Plumbing tie in will be taking place this Saturday 17th
Excavation 1.jpg

HDS header at nurses station installed

NEXT WEEK'S ACTIVITIES

    Install and complete the HDS headers in area A7
    Complete electrical rough in in area A6 and A5
    Start electrical rough in of area A7
    Start on siding of sheet rock for area A4 A5 and A6
    Relocate the sprinkler line in area A8 for fire wall install
Excavation 1.jpg

patch work of old penetration complete

Excavation 1.jpg

roof top unit in place, ready for there rough in and electrical