THIS WEEK'S ACCOMPLISHMENT
- Finishing up most of the new doorways in corridors
- Plumbing rough top side almost complete
-
-
-
-

New corridor walls and door ways going in
NEXT WEEK'S ACTIVITIES
- Start one siding sheetrock
- Sprinkler line relocation work
- One siding sheetrock in area A4 and A5
- Rework of the existing restrooms to accommodate for ADA
-

-
Electrical and plumbing rough of new Breakroom

Utility closet rough just about done for new washer and dryer room
LOOK AHEAD SCHEDULE