Weekly Project Update

BBTCS STEP DOWN 1/23/26

Placeholder

Keith Farrell

Jan 23, 2026

THIS WEEK'S ACCOMPLISHMENT

    Finishing up most of the new doorways in corridors
    Plumbing rough top side almost complete
Excavation 1.jpg

New corridor walls and door ways going in

NEXT WEEK'S ACTIVITIES

    Start one siding sheetrock
    Sprinkler line relocation work
    One siding sheetrock in area A4 and A5
    Rework of the existing restrooms to accommodate for ADA
Excavation 1.jpg

Electrical and plumbing rough of new Breakroom

Excavation 1.jpg

Utility closet rough just about done for new washer and dryer room

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.