top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

BBTCS STEP DOWN 1/30/2026

Placeholder

Keith Farrell

Jan 30, 2026

THIS WEEK'S ACCOMPLISHMENT

    All new opening for doors in the corridors installed
    Fire wall framing in family room completed
    Needed sprinkler line relocated in family room for the accessibility of the fire wall framing install
    Continued top out of plumbing in the dining and shower area
    All electrical rough completed in area A4,A5 and A6
Excavation 1.jpg

Fire wall install done after sprinkler pipe relocation

NEXT WEEK'S ACTIVITIES

    Start one siding all Rated walls and non rated wall in Area A4,A5,A6 and A8
    Continue the top out in are A7
    Install the floor drains for showers and restrooms in area A7
    Get the new wall layout for the kitchen area under way
Excavation 1.jpg

Plumbing top out of staff restroom done for area A6 breakroom

Excavation 1.jpg

Electrical rough done for Area A6

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page