Weekly Project Update
BBTCS STEP DOWN 1/30/2026

Keith Farrell
Jan 30, 2026
THIS WEEK'S ACCOMPLISHMENT
- All new opening for doors in the corridors installed
- Fire wall framing in family room completed
- Needed sprinkler line relocated in family room for the accessibility of the fire wall framing install
- Continued top out of plumbing in the dining and shower area
- All electrical rough completed in area A4,A5 and A6
-

Fire wall install done after sprinkler pipe relocation
NEXT WEEK'S ACTIVITIES
- Start one siding all Rated walls and non rated wall in Area A4,A5,A6 and A8
- Continue the top out in are A7
- Install the floor drains for showers and restrooms in area A7
- Get the new wall layout for the kitchen area under way
-

-
Plumbing top out of staff restroom done for area A6 breakroom

Electrical rough done for Area A6
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.