THIS WEEK'S ACCOMPLISHMENT
- Closing up sheetrock in area A4 and A5
- Hollow metal door frames install started
- All stud walls completed
- Plumbing insulation started will finish early next week
-
-

Lobby entry framing complete
NEXT WEEK'S ACTIVITIES
- Remaining framing inspections
- Start blocking work for all restrooms hand rails and accessories
- Continue closing up all walls that are ready
- Get rated wall board and screw inspections when ready
-

-
To deck sheetrock almost completed in all of area A5

Quiet rooms in area A7 all one sided and waiting there framing inspection to insolate and cover up