Weekly Project Update

BBTCS STEP DOWN 2/13/2026

Placeholder

Robert Chaison

Feb 13, 2026

THIS WEEK'S ACCOMPLISHMENT

    Closing up sheetrock in area A4 and A5
    Hollow metal door frames install started
    All stud walls completed
    Plumbing insulation started will finish early next week
Excavation 1.jpg

Lobby entry framing complete

NEXT WEEK'S ACTIVITIES

    Remaining framing inspections
    Start blocking work for all restrooms hand rails and accessories
    Continue closing up all walls that are ready
    Get rated wall board and screw inspections when ready
Excavation 1.jpg

To deck sheetrock almost completed in all of area A5

Excavation 1.jpg

Quiet rooms in area A7 all one sided and waiting there framing inspection to insolate and cover up

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.