Weekly Project Update

BBTCS STEP DOWN 2/20/2026

Placeholder

Robert Chaison

Feb 20, 2026

THIS WEEK'S ACCOMPLISHMENT

    Continued to rap up sheetrock in area A4
    Continued the install of hollow metal and timely door frames
    Electricians working on misc mc and low voltage piping for doors and power circuits
Excavation 1.jpg

Rocking out the restrooms in area A4 getting ready for tile work to start

NEXT WEEK'S ACTIVITIES

    Getting the frames installed for the hard lid ceilings in area A4 and A6
    Starting TFT in area A4
    Getting area A6 covered up and ready for TFT
    getting hard lid grid installed in area A5
Excavation 1.jpg

Hollow metal welded frames are going in and almost completed

Excavation 1.jpg

Timley frames are also getting installed and almost completed in area A4 and A6

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.