top of page


Weekly Project Update
BBTCS STEP DOWN 2/6/26

Robert Chaison
Feb 6, 2026
THIS WEEK'S ACCOMPLISHMENT
- Started hanging sheetrock one side
- Continued the plumbing top out work
- Framing inspection passed
- Electrical rough in inspection passed
- Getting control cabling for HVAC systems installed
-

Sheetrock going on the walls in the admission area
NEXT WEEK'S ACTIVITIES
- Start insolation and closing up walls
- Get plumbing top out interior completed
- Continue HVAC control cabling install
- Possibly T&F sheetrock walls later in the week for the walls completed
- Start the work of installing the grease trap for the kitchen

-
Therapy suits sheetrock going up

Looking in to the sleeping units activity room from the doorway
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page