Weekly Project Update

BBTCS STEP DOWN 2/6/26

Placeholder

Robert Chaison

Feb 6, 2026

THIS WEEK'S ACCOMPLISHMENT

    Started hanging sheetrock one side
    Continued the plumbing top out work
    Framing inspection passed
    Electrical rough in inspection passed
    Getting control cabling for HVAC systems installed
Excavation 1.jpg

Sheetrock going on the walls in the admission area

NEXT WEEK'S ACTIVITIES

    Start insolation and closing up walls
    Get plumbing top out interior completed
    Continue HVAC control cabling install
    Possibly T&F sheetrock walls later in the week for the walls completed
    Start the work of installing the grease trap for the kitchen
Excavation 1.jpg

Therapy suits sheetrock going up

Excavation 1.jpg

Looking in to the sleeping units activity room from the doorway

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.