Weekly Project Update

BBTCS step down

Placeholder

Keith Farrell

Nov 14, 2025

THIS WEEK'S ACCOMPLISHMENT

    Plumbing make safe and fixture demo
    Electric make safe
    Fire alarm make safe
    Started wall demo in all areas
    Removed glass and interior storefront frames
    Removed flooring in therapy suites area
Excavation 1.jpg

Demo in Therapy Suites

NEXT WEEK'S ACTIVITIES

    Complete Wall demo in all areas
    Remove all vct and carpet
    Start ceiling demo in all areas
    Remove wall tile in restrooms
    Remove remainder of hvac duct work
Excavation 1.jpg
    Set temp fencing in corridor to separate us from occupied space when wall is removed

Demo in Dining and Shower area

Excavation 1.jpg

Demo of carpet of Terrazzo flooring

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.