THIS WEEK'S ACCOMPLISHMENT
- Plumbing make safe and fixture demo
- Electric make safe
- Fire alarm make safe
- Started wall demo in all areas
- Removed glass and interior storefront frames
- Removed flooring in therapy suites area

Demo in Therapy Suites
NEXT WEEK'S ACTIVITIES
- Complete Wall demo in all areas
- Remove all vct and carpet
- Start ceiling demo in all areas
- Remove wall tile in restrooms
- Remove remainder of hvac duct work

- Set temp fencing in corridor to separate us from occupied space when wall is removed
Demo in Dining and Shower area

Demo of carpet of Terrazzo flooring
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.