THIS WEEK'S ACCOMPLISHMENT
- started CFMF in area A following is area F,B and D
- all above duct work completed and rough inspection done
-
-
-
-

CFMF starting to go down
NEXT WEEK'S ACTIVITIES
- continue CFMF in area F,D,B
- plumber under slab rough starting
- sprinkler head relocation to start
- electrical rough where possible
-

-
pier repair began

pier repair under way