Weekly Project Update

BBTCS STEPDOWN RENO

Placeholder

Keith Farrell

Dec 12, 2025

THIS WEEK'S ACCOMPLISHMENT

    started CFMF in area A following is area F,B and D
    all above duct work completed and rough inspection done
Excavation 1.jpg

CFMF starting to go down

NEXT WEEK'S ACTIVITIES

    continue CFMF in area F,D,B
    plumber under slab rough starting
    sprinkler head relocation to start
    electrical rough where possible
Excavation 1.jpg

pier repair began

Excavation 1.jpg

pier repair under way