top of page


Weekly Project Update
BBTCS STEPDOWN RENOVATION

Keith Farrell
Jan 9, 2026
THIS WEEK'S ACCOMPLISHMENT
- PLUMBING TOP OUT CONTINUING
- CFMF INSTALL CONTINUES IN ALL AREAS
- VAV UNIT CONFLICT RESOLVED AND RELOCATED
- UNDER SLAB PLUMBING INSTALL CONTINUES
-
-

PLUMBING TOPOUT UNDERWAY
NEXT WEEK'S ACTIVITIES
- PLUMBING TOP OUT CONTINUES
- CFMF INSTALL CONTINUES AND ONESIDING SHEETROCK
- PLUMBING TIE IN HAPPENING SATURDAY THE 17TH
- ELECTRICAL ROUGH IN CONTINUES
-

-
FRAMING IN AREA A7 DINING & SHOWERS

FRAMING UP IN AREA A6 THERAPY
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page