Weekly Project Update

BBTCS STEPDOWN RENOVATION

Placeholder

Keith Farrell

Jan 9, 2026

THIS WEEK'S ACCOMPLISHMENT

    PLUMBING TOP OUT CONTINUING
    CFMF INSTALL CONTINUES IN ALL AREAS
    VAV UNIT CONFLICT RESOLVED AND RELOCATED
    UNDER SLAB PLUMBING INSTALL CONTINUES
Excavation 1.jpg

PLUMBING TOPOUT UNDERWAY

NEXT WEEK'S ACTIVITIES

    PLUMBING TOP OUT CONTINUES
    CFMF INSTALL CONTINUES AND ONESIDING SHEETROCK
    PLUMBING TIE IN HAPPENING SATURDAY THE 17TH
    ELECTRICAL ROUGH IN CONTINUES
Excavation 1.jpg

FRAMING IN AREA A7 DINING & SHOWERS

Excavation 1.jpg

FRAMING UP IN AREA A6 THERAPY

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.