Weekly Project Update
Bluebonnet Trails Crisis Center San Gabriel Remodel

Steven Conrad
Oct 10, 2025
THIS WEEK'S ACCOMPLISHMENT
- Demoed damaged flooring from the office spaces
- Demoed the damaged sheetrock in the mechanical rooms
- Painted the office spaces
- Installed new drywall in the mechanical rooms
-
-

NEXT WEEK'S ACTIVITIES
- Install new flooring and base molding in the office spaces
- Paint the mechanical rooms
-
-
-

-

LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.