THIS WEEK'S ACCOMPLISHMENT
- Make safe and demo electrical, plumbing, HVAC, and fire/smoke alarms
- Demo CMU walls
- Demo and Abatement of existing LVL flooring
-
-
-

Wall between existing bedroom and med room demoed
NEXT WEEK'S ACTIVITIES
- Demo concrete slab for remaining plumbing demo
- Plumbing rough-in
- Build new CMU walls
-
-

-
Restroom 01 laid out and ready for the floor to be demoed for plumbing rough-in

Shower room 07 ready for the floor to be demoed for plumbing rough-in