Weekly Project Update

Bluebonnet Trails Diversion Center Georgetown Remodel

Placeholder

Steven Conrad

Nov 7, 2025

THIS WEEK'S ACCOMPLISHMENT

    Make safe and demo electrical, plumbing, HVAC, and fire/smoke alarms
    Demo CMU walls
    Demo and Abatement of existing LVL flooring
Excavation 1.jpg

Wall between existing bedroom and med room demoed

NEXT WEEK'S ACTIVITIES

    Demo concrete slab for remaining plumbing demo
    Plumbing rough-in
    Build new CMU walls
Excavation 1.jpg

Restroom 01 laid out and ready for the floor to be demoed for plumbing rough-in

Excavation 1.jpg

Shower room 07 ready for the floor to be demoed for plumbing rough-in

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.