THIS WEEK'S ACCOMPLISHMENT
- Install wall tile in Shower Room 07 & 08
- Install shower valves to complete plumbing top out
- Infill the old door in the staff office
- Fur out the walls in Corridor 05
- Relocate fire sprinklers
- First coat tape and float new walls in Corridor 05 and Day Room

NEXT WEEK'S ACTIVITIES
- Epoxy Restroom 01 and Shower Rooms 07 & 08 floors
- Finish tile work in showers
- Install ceilings
- Install plumbing fixtures
- Install new handrail

-

LOOK AHEAD SCHEDULE