Weekly Project Update

Bluebonnet Trails Diversion Center Georgetown Remodel

Placeholder

Steven Conrad

Dec 12, 2025

THIS WEEK'S ACCOMPLISHMENT

    Install wall tile in Shower Room 07 & 08
    Install shower valves to complete plumbing top out
    Infill the old door in the staff office
    Fur out the walls in Corridor 05
    Relocate fire sprinklers
    First coat tape and float new walls in Corridor 05 and Day Room
Excavation 1.jpg

NEXT WEEK'S ACTIVITIES

    Epoxy Restroom 01 and Shower Rooms 07 & 08 floors
    Finish tile work in showers
    Install ceilings
    Install plumbing fixtures
    Install new handrail
Excavation 1.jpg

Excavation 1.jpg

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.