Weekly Project Update
Bluebonnet Trails Diversion Center Georgetown Remodel

Steven Conrad
Dec 19, 2025
THIS WEEK'S ACCOMPLISHMENT
- Epoxy Restroom 01 and Shower Rooms 07 & 08 floors
- Install ceilings
- Install plumbing fixtures
- Install new handrail
- Install new LVT flooring in Corridor 05
-

NEXT WEEK'S ACTIVITIES
- Install tile in shower pans & on shower valve walls
- Install shower heads
- Install grab bars
- Install new LVT in Corridor 09
- Inspections

-

LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.