THIS WEEK'S ACCOMPLISHMENT

    Electrical Rough-In
    Shower Room Slab Pour Back
    Install Door Frames and CMU
    Install Ceiling Grid in IT Closet and Bedroom Unit
Excavation 1.jpg

4 in. shower wall and new plumbing chase framed in Shower Room 08

NEXT WEEK'S ACTIVITIES

    Frame Plumbing Chase Walls in Shower Room 07 and Restroom 01
    Install Ceiling Grid in Meds Storage
    Finish out new IT Closet
    Start tile work in Restrooms
Excavation 1.jpg

IT Closet with first coat of paint and new ceiling grid

Excavation 1.jpg

Shower Room 07 with new door and 4 in. shower wall

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.