Weekly Project Update
Bluebonnet Trails Diversion Center Georgetown Remodel

Steven Conrad
Nov 28, 2025
THIS WEEK'S ACCOMPLISHMENT
- Electrical Rough-In
- Shower Room Slab Pour Back
- Install Door Frames and CMU
- Install Ceiling Grid in IT Closet and Bedroom Unit
-
-

4 in. shower wall and new plumbing chase framed in Shower Room 08
NEXT WEEK'S ACTIVITIES
- Frame Plumbing Chase Walls in Shower Room 07 and Restroom 01
- Install Ceiling Grid in Meds Storage
- Finish out new IT Closet
- Start tile work in Restrooms
-

-
IT Closet with first coat of paint and new ceiling grid

Shower Room 07 with new door and 4 in. shower wall
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.