THIS WEEK'S ACCOMPLISHMENT

    Completed temporary electric panel in health science
    Installed millwork health science area
    Installed flooring health science area
    Started All roof top AC units
    Installed electric panel in Bistro
    Turned on lights in health science area
Excavation 1.jpg

Electric panel in Bistro

NEXT WEEK'S ACTIVITIES

    Plumbing fixtures in health science area
    Finish paint in health science area
    Receive vent hoods
    Paint wall cafeteria side of bistro for three form and lettering
    Start vent hood install
Excavation 1.jpg
    Receive ceiling tile

Millwork health science area

Excavation 1.jpg

Flooring health science area

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.