top of page


Weekly Project Update
CEDAR RIDGE CTE

Keith Farrell
THIS WEEK'S ACCOMPLISHMENT
- Completed temporary electric panel in health science
- Installed millwork health science area
- Installed flooring health science area
- Started All roof top AC units
- Installed electric panel in Bistro
- Turned on lights in health science area

Electric panel in Bistro
NEXT WEEK'S ACTIVITIES
- Plumbing fixtures in health science area
- Finish paint in health science area
- Receive vent hoods
- Paint wall cafeteria side of bistro for three form and lettering
- Start vent hood install

- Receive ceiling tile
Millwork health science area

Flooring health science area
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.