Weekly Project Update

Cele MS Safe Sidewalks

Placeholder

Jeff Rubino

Jul 18, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished All Concrete Work
    Installed Truncated Domes
    Roughed-In Light Pole Base
Excavation 1.jpg

Truncated Domes

NEXT WEEK'S ACTIVITIES

    Final Grading
    Cleanup
    Light Pole Install
Excavation 1.jpg

Light Pole Base

Excavation 1.jpg

Final Grade

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.