Weekly Project Update

Cele MS Safe Sidewalks

Placeholder

Jeff Rubino

Jul 4, 2025

THIS WEEK'S ACCOMPLISHMENT

    Poured 130 CY of Concrete
    New Light Pole Was Roughed-In
    Continued Backfilling Around Previously Poured Sidewalk
Excavation 1.jpg

Pouring the Sidewalk by the School Entrance

NEXT WEEK'S ACTIVITIES

    Finish Pouring Sidewalks (40 YDS)
    Pour Apron's, Access Ramps, & Light Pole Base
    Continue Backfilling Around Previously Poured Sidewalk
    Start Revegitation
Excavation 1.jpg

Light Pole Stub Out

Excavation 1.jpg

Finished Concrete

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.