top of page


Weekly Project Update
Cele MS Safe Sidewalks

Jeff Rubino
Jul 4, 2025
THIS WEEK'S ACCOMPLISHMENT
- Poured 130 CY of Concrete
- New Light Pole Was Roughed-In
- Continued Backfilling Around Previously Poured Sidewalk
-
-
-

Pouring the Sidewalk by the School Entrance
NEXT WEEK'S ACTIVITIES
- Finish Pouring Sidewalks (40 YDS)
- Pour Apron's, Access Ramps, & Light Pole Base
- Continue Backfilling Around Previously Poured Sidewalk
- Start Revegitation
-

-
Light Pole Stub Out

Finished Concrete
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page