Weekly Project Update

Cele MS Safe Sidewalks

Placeholder

Jeff Rubino

Jul 25, 2025

THIS WEEK'S ACCOMPLISHMENT

    Light Pole Install
    Final Grading
    Cleanup
Excavation 1.jpg

Final Grade Between Ag Barn & Football Field (Laydown Yard & Concrete Washout)

NEXT WEEK'S ACTIVITIES

    Final Grading
    Revegetation
Excavation 1.jpg

Final Grade by School Entrance

Excavation 1.jpg

New Light Pole

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.