THIS WEEK'S ACCOMPLISHMENT

    Finished Forms
    Finished Demoing Curbs
    Continued Backfilling
Excavation 1.jpg

Access Ramp Forms (Rebar Install on Monday)

NEXT WEEK'S ACTIVITIES

    Pour Concrete
    Install Light Pole
    Finish Backfill
Excavation 1.jpg

Backfill on SE Side of Football Field

Excavation 1.jpg

Curb Demo

LOOK AHEAD SCHEDULE