THIS WEEK'S ACCOMPLISHMENT
- Completed structural roof framing above apparatus bay.
- Placed concrete in footers for rock, and retaining walls at parking area.
- Received decking material.
- Passed structural steel inspection at apparatus bay.
- Pulled wire for building temporary power.
- Formed curbs for paving at parking area.

Forming retaining wall at parking area.
NEXT WEEK'S ACTIVITIES
- Complete reinforcing steel at parking area.
- Complete decking above apparatus bay
- Place concrete at parking area.
- Form and install reinforcement steel at public parking and east drive.
- Place concrete at east drive and public parking.

-
Rebar at parking area.

Began decking above apparatus bay.