THIS WEEK'S ACCOMPLISHMENT

    Completed structural roof framing above apparatus bay.
    Placed concrete in footers for rock, and retaining walls at parking area.
    Received decking material.
    Passed structural steel inspection at apparatus bay.
    Pulled wire for building temporary power.
    Formed curbs for paving at parking area.
Excavation 1.jpg

Forming retaining wall at parking area.

NEXT WEEK'S ACTIVITIES

    Complete reinforcing steel at parking area.
    Complete decking above apparatus bay
    Place concrete at parking area.
    Form and install reinforcement steel at public parking and east drive.
    Place concrete at east drive and public parking.
Excavation 1.jpg

Rebar at parking area.

Excavation 1.jpg

Began decking above apparatus bay.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.