Weekly Project Update

CoRR Station 10

Placeholder

Richard Huddleston

Feb 16, 2026

THIS WEEK'S ACCOMPLISHMENT

    Completed CMU on West side of the building.
    Install structural steel roof framing above work room and fitness rooms.
    Hydro tested on fire riser line.
    Installed roof trusses above living quarters.
    Completed demo of phase 2 Exxon drive.
    Excavated for paving strip on north end of the property.
Excavation 1.jpg

CMU complete on west side of Apparatus Bay.

NEXT WEEK'S ACTIVITIES

    Complete subgrade at Exxon drive.
    Complete CMU on east side of apparatus bay.
    Install exterior surface blocking to prepare for waterproofing.
    Form and install reinforcement at Exxon drive.
    Flow test hydrants and fire riser.
Excavation 1.jpg
    Place concrete at Exxon drive

Completed demo at Exxon drive.

Excavation 1.jpg

Crane onsite to lift roof trusses.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.