top of page


Weekly Project Update
CoRR Station 10

Richard Huddleston
Feb 16, 2026
THIS WEEK'S ACCOMPLISHMENT
- Completed CMU on West side of the building.
- Install structural steel roof framing above work room and fitness rooms.
- Hydro tested on fire riser line.
- Installed roof trusses above living quarters.
- Completed demo of phase 2 Exxon drive.
- Excavated for paving strip on north end of the property.

CMU complete on west side of Apparatus Bay.
NEXT WEEK'S ACTIVITIES
- Complete subgrade at Exxon drive.
- Complete CMU on east side of apparatus bay.
- Install exterior surface blocking to prepare for waterproofing.
- Form and install reinforcement at Exxon drive.
- Flow test hydrants and fire riser.

- Place concrete at Exxon drive
Completed demo at Exxon drive.

Crane onsite to lift roof trusses.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page