THIS WEEK'S ACCOMPLISHMENT
- Completed Lighting Pathways
- Completed Interior Framing
- Completed Sheetrock Ceilings and Walls
- Completed Demo of Hallway Carpet
- Installed Hollow Metal Door Frame
- Completed Access Control Pathways

Display Case Sheetrock
NEXT WEEK'S ACTIVITIES
- Tape and Float Ceilings and Walls
- Install Access Control Wiring
- Install Grid Ceiling
- Pour Concrete Landing at Entrance
- Begin Paint

-