THIS WEEK'S ACCOMPLISHMENT
- Finished painting door frames
- Finished toilet partitions
- Finished plumbing Fixtures
- Finished hand dryers
- Finished toilet accessories
- Started acoustic panels in theater

Acoustic panels in theater
NEXT WEEK'S ACTIVITIES
- Finish acoustic panel
- Finish moving furniture
- Finish Cleaning
- Make punch list
- Remove all material

- complete punch list