Weekly Project Update

DEssau Middle School

Placeholder

Keith Farrell

Jul 12, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished all LVT
    Sealed all wood for locker room benches
    Finished paint in admin area
    Finished ceramic tile in all single restrooms
    Finished painting in theater room
    Finished ceramic tile in locker rooms
Excavation 1.jpg

LVT in theater area

NEXT WEEK'S ACTIVITIES

    Tape and float sheet rock ceilings in gang restrooms
    Clean admin area move furniture in
    Move all furniture back in classrooms
    Paint window and door frames in library
    Finish paint in band hall area
Excavation 1.jpg
    Set plumbing fixtures

Plumbing fixtures in locker rooms

Excavation 1.jpg

Finished carpet and furniture in library

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.