THIS WEEK'S ACCOMPLISHMENT
- Finished classroom flooring
- finished flooring and base in admin area
- epoxy floor in girls locker room
- finished prep and texture admin area
- Carpet in library
- drywall grid in restrooms

Ceramic floor tile in small restrooms
NEXT WEEK'S ACTIVITIES
- Sheet rock ceilings in restrooms
- Finish flooring in band hall area
- Cove base in library
- Ceramic tile in rest rooms
- Paint in A hall classrooms

- clean C&D hall classrooms
floor prep in band hall area

Carpet begins in library
LOOK AHEAD SCHEDULE