Weekly Project Update
Dessau Middle School

Keith Farrell
Jun 28, 2025
THIS WEEK'S ACCOMPLISHMENT
- Demo of acoustical panels in theater
- Finished floor prep in A hall classrooms for LVT
- Floor prep in locker room showers for epoxy
- Finished laying all LVT in admin area
- Finished cove base in D hall classrooms
- Finished Ceiling Tile replacement in A corridor and cafeteria corridor

Admin area LVT
NEXT WEEK'S ACTIVITIES
- Finish all epoxy floors
- Finish LVT in A hall classrooms
- prep performing arts area for LVT
- Finish paint in A hall classrooms
- Finish cove base in finished classrooms

- Tile begin in special classroom restroom
First coat of epoxy in girls locker room

Finished classroom
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.