Weekly Project Update

Dessau Middle School

Placeholder

Keith Farrell

Jun 28, 2025

THIS WEEK'S ACCOMPLISHMENT

    Demo of acoustical panels in theater
    Finished floor prep in A hall classrooms for LVT
    Floor prep in locker room showers for epoxy
    Finished laying all LVT in admin area
    Finished cove base in D hall classrooms
    Finished Ceiling Tile replacement in A corridor and cafeteria corridor
Excavation 1.jpg

Admin area LVT

NEXT WEEK'S ACTIVITIES

    Finish all epoxy floors
    Finish LVT in A hall classrooms
    prep performing arts area for LVT
    Finish paint in A hall classrooms
    Finish cove base in finished classrooms
Excavation 1.jpg
    Tile begin in special classroom restroom

First coat of epoxy in girls locker room

Excavation 1.jpg

Finished classroom

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.