Weekly Project Update

Eanes Administration Building

Placeholder

James Castillo

Jul 7, 2025

THIS WEEK'S ACCOMPLISHMENT

    Poured foundation for exterior stairs
    Poured front entry sidewalk
    Started exterior stair erection
    Started interior wood stairs
    Painted roof deck at second floor
    Started ceramic tile at second floor restrooms
Excavation 1.jpg

NEXT WEEK'S ACTIVITIES

    Finish exterior stairs
    Continue with ceramic tile in restrooms
    Continue wood stairs
    Start elevator
Excavation 1.jpg

Excavation 1.jpg

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.