Weekly Project Update
EANES E.S. WINDOW REPLACEMENT PHASE 2

Pat Tims
THIS WEEK'S ACCOMPLISHMENT
- MILLWORK INSTALLED BUILDING I CLASSROOMS
- REMAINING CLASSROOM DOORS PAINTED BUILDING K
- FINAL CLEAN BUILDINGS H,I, & K CLASSROOMS
- CLEANED GROUNDS OF ALL CONSTRUCTION DEBRIS
-
-

MILLWORK BUILDING I
NEXT WEEK'S ACTIVITIES
- REMOVE DUMPSTER
- EANES I.S.D. WALK THROUGH
-
-
-

-
FINAL CLEAN ALL CLASSROOMS

OVERALL LOOK OF NEW WINDOWS BUILDING I
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.